Decision details

DLEP - FWP Corridor Programme

Decision Maker: Cabinet

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To consider report detailing the proposed Ferndown, Wallisdown & Poole (FWP) Corridor Programme and approve request to add scheme and associated secured DLEP funding provision to 2020/21 LTP Capital Programme for delivery.

Decision:

RESOLVED that Cabinet:-

(a)          Noted the Dorset Local Enterprise Partnership (DLEP) Funding allocation of £1,050,000; and

(b)          approved the progression of detailed design and stakeholder engagement for the Wallisdown Road scheme in line with the key project aims identified and General Arrangement drawing included in Appendix A of the report.

Voting: Unanimous

Portfolio Holder: Transport and Infrastructure

Reasons

1.      To add the funding allocation to the 2020/21 LTP Capital Programme and enable its full utilisation within the DLEP Growth Deal funding period (before 31 March 2021).

2.      Addition of £502,500 to the Blackwater West Junction scheme as a result of reallocating DLEP funding across BIG Programme schemes enables the recrediting of already committed local funding contributions, which will result in greater flexibility of spend (local contributions to the BIG programme can be spent beyond the DLEP funding deadline of 31 March 2021).

3.      To enable the development and progression of the FWP: Wallisdown Road based scheme within the required timescales.


Portfolio Holder: Transport and Infrastructure

 

Report author: Tim Forrester

Publication date: 11/09/2020

Date of decision: 09/09/2020

Decided at meeting: 09/09/2020 - Cabinet

Effective from: 19/09/2020

Accompanying Documents: