Fulfilled Lives Programme Update

Meeting: 23/09/2025 - Health and Adult Social Care Overview and Scrutiny Committee (Item 9.)

9. Adult Social Care Fulfilled Lives Transformation Programme pdf icon PDF 938 KB

In July 2024, BCP Cabinet and Full Council agree to support a four-year transformation programme called Fulfilled Lives, approving a total investment of £2.9m spanning the first three years.

The programme is made up of four inter-dependent projects:

·       How We Work

·       Short-Term Support

·       Self-Directed Support

·       Support At Home

An initial investment of £1.79m for the first 12 months of the programme was agreed, with progress monitored on a minimum six-monthly basis by members of the Health and Adult Social Care Overview & Scrutiny Committee.

The programme entered its delivery phase in January 2025 and, since then, progress reports were presented to Committee in January, March and July.

The release of the remaining £1.11m funding for the programme was approved by Cabinet and Full Council in July 2025, and this report provides a further brief update for the programme overall including a deeper focus, as requested, on the Self-Directed Support and Short-Term Support projects.