This report details progress made on delivery of the 2025/26 Audit Plan for the 2nd quarter (July to September 2025 inclusive). The report highlights that:

·       18 audit assignments have been finalised, including 16 ‘Reasonable’ and two ‘Partial’ audit opinions;

·       25 audit assignments arein progress, including 3 at draft report stage;

·       Progress against the audit plan is on track and will be materially delivered to support the Chief Internal Auditor’s annual audit opinion;

·       10 ‘High’ priority auditrecommendations have not been fully implemented by the original target date and 3 ‘Medium’ priority recommendations have (or will) not be implemented within 18 months of the original target date. Explanations from respective services have been provided and revised target dates have been agreed.

 