7. External Auditor – Audit Progress & Sector Update
PDF 295 KB
Grant Thornton, as the Council’s appointed External Auditors, have produced a report (Appendix A) which provides an update to Audit & Governance Committee on their progress to date in delivering their responsibilities.
The report includes an update on their audit work. Key points of note are:
· Financial Statements Audit 2024/25
o Work on the financial statement audit is nearly complete.
o The audit findings report is being reported to the Audit & Governance Committee alongside this progress report.
o The value for money audit is complete and was included in the interim annual auditor report (AAR) presented to this committee in Nov 2025.
o The AAR report will be updated to include key financial statement audit findings and then issued in final form.
· Financial Statements Audit 2025/26
o Plan to undertake planning and early testing prior to the year end to support an earlier completion.
o In order to prepare for the backstop moving forward over the next two years, plan to finalise the 2025/26 audit by November 2026.
The report also includes a summary of emerging national issues and developments that may be relevant to the Council.