58 Adult Social Care Fulfilled Lives Transformation Programme
PDF 466 KB
In July 2024, BCP Cabinet and Full Council agree to support a four-year transformation programme called Fulfilled Lives, approving a total investment of £2.9m spanning the first three years.
The programme is made up of four inter-dependent projects:
· How We Work
· Short-Term Support
· Self-Directed Support
· Support At Home
The programme entered its delivery phase in January 2025 and progress reports were presented to Committee in January, March, July and September.
This report provides a further update for the programme overall to reflect the achievements to date, the current challenges, and the next steps to be taken over the following six months.
Minutes:
The Head of Service/Programme Lead for the Fulfilled Lives Transformation Programme presented a report, a copy of which had been circulated to each Member a copy of which appears as Appendix 'C' to these Minutes in the Minute Book.
In July 2024, BCP Cabinet and Full Council agreed to support a four-year transformation programme called Fulfilled Lives, approving a total investment of £2.9m spanning the first three years.
The programme was made up of four inter-dependent projects:
· How We Work
· Short-Term Support
· Self-Directed Support
· Support At Home
The programme entered its delivery phase in January 2025 and progress reports were presented to Committee in January, March, July and September.
The report provided a further update for the programme overall to reflect the achievements to date, the current challenges, and the next steps to be taken over the following six months.
The Committee considered the report, including:
RESOLVED that the Committee note the current work-in-progress with the Adult Social Care Fulfilled Lives Programme.
Voting: Nem Con